FDEP agreed to waiver on Lido Renourishment Project timeline because it wanted more time to review materials related to the application, city engineer says

By Rachel Brown Hackney SarasotaNewsLeader.com The reason the Florida Department of Environmental Protection (FDEP) agreed to extend by 30 days a decision on its next step in the Lido Renourishment Project permit process was because staff wanted more time to Read More

Big Pass Dredging

Site for Seagrass Mitigation, Perico Preserve  By SKA Environmental Committee Several hurdles remain since the U.S. Army Corps of Engineers (USACE) requested a second six–month extension of its Florida Department of Environmental Protection (FDEP) Dredging Permit application.  When a previous Read More